Mitigation Measures in Dealing with Delays and Cost Overrun in Public Building Projects in Dar-Es-Salaam, Tanzania

Jaffari S. Jongo1, Dennis N. G. A. K. Tesha2, Raymond Kasonga1, Justine J. Teyanga1, Kenan S. Lyimo2

1School of Architecture Construction Economics and Management (SACEM), Department of Interior Design, ARDHI University (ARU), Dar-Es-Salaam, Tanzania

2School of Architecture Construction Economics and Management (SACEM), Department of Building Economics, ARDHI University (ARU), Dar-Es-Salaam, Tanzania

Correspondence to: Dennis N. G. A. K. Tesha, School of Architecture Construction Economics and Management (SACEM), Department of Building Economics, ARDHI University (ARU), Dar-Es-Salaam, Tanzania.

Email:

Copyright © 2019 The Author(s). Published by Scientific & Academic Publishing.

This work is licensed under the Creative Commons Attribution International License (CC BY).
http://creativecommons.org/licenses/by/4.0/

Abstract

A building construction project is a high risk activity which must be managed effectively in all stages, in order to avoid delays and cost overruns, which in most cases are part of it, and a common problem. These problems occur frequently during project life-time leading to disputes and litigation. There are numerous factors causing delays and cost overrun in building construction projects, and in order to mitigate these causes; the study aimed at identifying the mitigation measures in dealing with delay and cost overrun in public building project in Dar-Es-Salaam, Tanzania. This research presents a list of construction delay and cost overrun causes and mitigation retrieved from literature. The feedback from building construction experts was obtained through questionnaires. Subsequently, a questionnaire containing list of construction delays and cost overrun mitigations retrieved from literature was prepared. The questionnaire survey was distributed to 75 building construction experts, from the clients, consultants, and contractor’s organizations side. Out of 75 distributed questionnaires, only 49 were returned. The data were analysed using Microsoft excel and ranked according to mean score for contractor, consultant and client. The general response from both parties were analysed, high scored factors were discussed. Effective project planning and scheduling; design change should be controlled; effective coordination and communication between parties; client, promptly paying the parties progressively; having accurate cost estimates; appoint competent site and project manager; comprehensive contract administration; ensuring prompt resolution in design change queries, issues and authorization report; efficient and effective planning time schedule for material procurement delivery process; developing effective strategic planning for solving identified risks; and ensuring on the timely availability of finance; were identified as the most effective mitigation measures in dealing with delay and cost overrun in public building project, due to having a mean score above 4.00.

Keywords: Mitigation Measures, Delays, Cost Overrun, Construction, Building Projects, Dar-Es-Salaam, Tanzania

Cite this paper: Jaffari S. Jongo, Dennis N. G. A. K. Tesha, Raymond Kasonga, Justine J. Teyanga, Kenan S. Lyimo, Mitigation Measures in Dealing with Delays and Cost Overrun in Public Building Projects in Dar-Es-Salaam, Tanzania, International Journal of Construction Engineering and Management , Vol. 8 No. 3, 2019, pp. 81-96. doi: 10.5923/j.ijcem.20190803.01.

1. Introduction

Delay and cost overruns are common issues in the building construction industry, in developed and developing countries, [1, 6, 19, 29, 30, 50, 62]. This makes it difficult for building construction projects, which in most cases are complex endeavours, associated with large costs and long duration, to achieve their major criteria in terms of success (i.e. project completion within budget, time, best quality and the satisfaction of the client’s requirement), [18, 59, 66, 69] asserts that; the achievement of these project success in the building construction industry, is even more critical, as companies work on narrow margins. They further insist that; even with various cost control software and techniques, delay and cost overruns still prevail in building construction projects.
Moreover, [45, 58, 59] reports that; during the last few decades, numerous project control method such as Grantt Bar Chart, Programmed Evaluation and Review Technique (PERT) and Critical Path Method (CPM) have been developed; and a variety of software packages have become available to support the application of these project control method, for example Microsoft Project, Asta Power Point, Primavera etc. Despite the wide use of these software and method, many construction projects still suffer extensive delay and cost overrun. The delay and cost overrun issue in building construction industry is also enlightened by, [12, 34, 46] writings as they portray how over the years, it has been a challenge worldwide, with the inability to complete the project on time, and within budget being a chronic key problem, despite the advent of advanced technology and construction management techniques.
Most authors affirm that; building construction project usually present delays and time overrun. [18] underlines that; building construction project is a complex task undertaken by participants from multi-discipline construction professionals, which involve construction project control by constantly measuring progress, evaluating plans and taking corrective action when required, and ensuring that the targeted project objectives are achieved without delay and cost overruns. Moreover, despite building construction project involves huge contract values, more specialized works, tighter schedule, stringent quality standards, etc. as per [18], it is rarely to find construction project completed without cost and time overrun; because there are some instances were construction project are completely unpredictable, [6]. Furthermore, [43] contends that; the project contractors and owners do not use management methodologies that are useful to distribute resources properly. Even though the management of project has been studied for many years, most project either failed or present cost or time overrun. [65] insists that; these overruns are considered as critical issues in the construction business, because they represent the loss of money for contractors and owners.
In Sub-Saharan Africa, delay and cost overrun have been observed in different countries. Studies by [12, 31, 55] conducted in Nigeria, South Africa and Ghana, revealed that; most building projects are completed at the cost much higher than initial cost estimate and out of the budget; failure in delivering the project on time; and cost and time overrun existing in more than 40% of building construction project. According to [38, 46] delays and disruption are among the challenges faced in the course of executing construction projects in Sub-Saharan Africa. It may sometimes exceed 100% of the anticipated cost of the project. Additionally [38, 46] reports that; Tanzania also face challenges on importation of industrial plants and equipment, due to its unlimited purchasing power caused by foreign exchange problems, that leads to some of building construction works previously planned, encountering with delays and cost overruns. Also [42, 46] affirm that; the extent of poor planning, contributes to the delay on construction works in Tanzania, causing wastage of time and money, that results to price escalation.
Numerous studies by [13, 38, 61] on delay and cost overrun in building construction industry have been conducted, focusing on identifying factors that leads to delays and cost overrun, and none has been done on mitigation measures in dealing with delays and cost overrun in public building projects.

1.1. Problem Statement

The building construction industry in Tanzania, contributes greatly to the overall economy, but it is plagued by delay and cost overrun due to various causes. [47] asserts that; the construction industry contributed 13.6% to Tanzania’s GDP during 2015, reaching almost USD6 Billion, and in 2010 the sector accounted for only 7.8% of the country’s GDP or USD1.6 Billion. In order for the industry to effortlessly growth more and add more value to the country’s economy, delay and cost overruns which are common in building construction industry must be mitigated, because they have been, and continues to be a major problem to both private and public building projects; resulting into shortfall on meeting the original budget, and the expected client satisfaction, [46]. According to [19]; delay and cost overruns during the building construction phase may seriously over-extend the client financially, resulting to a failure or an unfinished building project as per the expected standards, or may even have to be abandoned.
Moreover, [19] adds that; the fact that delay and cost overruns reduce the effectiveness of building investments, alongside demanding additional finance due to an additional building construction cost, makes it even more important on studying its mitigations. Moreover, [19, 22, 46] affirms more on the importance of mitigating the delay and cost overrun as they trigger incapacitating effect on clients, consultant and contractor in terms of growth in adversarial relationship among project participants, mistrust, disputes, litigation, arbitration, cash-flow problems, frustrating project objectives, and a general feeling of trepidation toward each other. Furthermore, as non-mitigation of delay and cost overruns in building construction, results to unanticipated and unexpected impact, [48, 64]. Therefore; this study focuses on identifying by ranking the mitigation measures in dealing with delay and cost overrun in public building project in Dar-Es-Salaam, Tanzania, through mean score.

2. Delay and Cost Overruns in Building Construction

[17] reports that; a construction project is a high value, time bound, special construction mission of creating a construction facility or service, with predetermined performance objectives defined in terms of quality specification, completion time, budgeted cost and other specified constraints. Cost and time are among five main parameters that can sufficiently define a construction project. Other parameters are scope, quality and resources. The five parameters are interactive, in which each parameter is a function of other. The evaluation and balancing of interrelationship among the five project parameters is a complicated process. However, in a given project, the scope and quality of work in terms of quantity and specifications are specified and these parameters are not subjected to change (unless scope changes substantially), [70]. Resources and costs are co-related. Therefore, for a given quality, in such situation, time, cost and scope are core parameters. These parameters are interlinked and must be kept in balance to achieve project objective efficiently and effectively within changing environments, [17]. Moreover, organizations face a major challenge in controlling building project budgets over the time span between project initiation and the completion of construction. The development of time and cost estimates that accurately reflect project scope, economic conditions, and are attuned to community interest and the macroeconomic conditions provide a baseline cost and time that management can use to impart discipline into the design process. [68] asserts that; one of the most vital tasks for completing a project successfully is to have a good management of construction cost in order to avoid delay and cost overruns.

2.1. Cost Overrun

Cost Overrun or “Cost Escalation”, or “Cost Increase”, or “Budget Overrun”, is defined as excess of actual cost over budget, [46]. Basically, it happens when the final cost of the project exceeds the original approved cost estimates, unlike the client’s expectations, [19, 46]. [46] also details that; cost overrun may also be defined as the change in contract amount, divided by the original contract award amount; OR the difference between the actual cost and the initially projected cost, whereby its calculations can be converted to a percentage (%) for ease comparison. [42] defines cost overrun as the difference between the final actual cost of construction project at completion, and the contract amount agreed between the client and the contractor during signing of the contract, is used. [66] affirms that; the cost of building construction project which in most cases its growth is “amoebic” in nature, escalating in an exponential manner and not linearly, is affected by a large number of factors, making it a bit difficult in tracking down, what drives total cost overrun.
Basically, a global problem as most of the construction industry around the world, do exceeds the expected budget often. A global study by [25, 68] on construction projects has found that; cost overrun is the most faced problem, with an estimation of 9 out of 10 projects facing the problem with an overrun of 50% to 100%. Likewise, another investigation on 87 projects conducted by [68] has revealed that; the problem of cost overrun exists in projects by an average of 10.3%, giving an example of the United Kingdom (UK) where nearly one third of all clients files complains about their projects exceeding their allocated budget. Malaysia is also another country being affected severely by cost overrun, in which only 46.8% of public sector and 37.2% of private sector projects are being finished within the allocated budget, [64, 68].

2.2. Delay or Time Overrun

Delay or Time Overrun in building construction project is the late in progress or actual completion of work, compared to the baseline construction schedule or contract schedule, [46], i.e. the non-completion of building projects on time by the contractor, [22]. Moreover, they assert that; majority of project delays occur during the construction phase, where many unforeseen factors are always involved. [42] defined “Time Overrun”, as the difference between the Actual Project Duration and the Estimated Project Duration. According to [14] the term ‘delay’ in construction contracts has no precise technical meaning, as it can be used in different sense refereeing different conditions in project execution. However, the term is often used in its basic sense to mean any occurrences or events that extend the duration or delay the start or finish of any of the activities of a project, [46]. [22], claims that; apart from delays being rampant across the world, they are invariably accompanied by cost and time overruns.

2.3. Types of Delay or Time Overrun

[15] details there are four types of construction delay encountered in building projects, which includes:-
a) Excusable delay or non-excusable delay,
b) Concurrent delay or non-concurrent delay,
c) Compensable delay and non-compensable delay, and
d) Critical delay or non-critical delay.
Excusable Delay; as per [15], are unforeseeable events which are beyond anyone control, and they are broken down into compensable and non-compensable delays. If the delay is considered to be compensable, then the contractor is entitled to compensate the additional financial and extra time, but when the delay is uncompensated excusable delay the contractor will receive extra time but not extra money. Likewise, [69] narrates that; excusable delays are occurrences over which neither the owner, nor the contractor have any control, giving example of extreme weather conditions, acts of God and other unforeseen future events.
Non-Excusable Delay; [15], reports that; these are foreseeable from which the activities or events are within the control of the contractor. In case of this situation the contractor is not able to receive any extra time or compensation for the work. The owner and designer are liable to make sure that the contract document are made clear. Excusable and non-excusable delay can occur concurrent, non-concurrent or simultaneously in a project. Concurrent delays occur at the same time or close to the same time. They can also contain critical and non-critical delays. Critical delays are delay claims that they affect the progress time and compensation. Non-critical delays do not affect the completion date of the project. They affect the succeeding activities that are not on the critical path of the schedule. [69] details in this case; apart from the main contractor being entitled neither to time extension nor to monetary recompense from the owner, may end up paying liquidated damages according to the contract.
Concurrent Delay; [1] narrates that; these are delay which occur at the same time or close to the same time that is when one factor delays the project at the same time or in overlapping periods of time. This delay is caused by the owner and the contractor.
Compensable Delay; [27] underlines that; these are delays which caused due to inadequate drawings and a specification which arises from the owner failure to respond in a timely request for information or owner may cause changes in design or materials. These delays are compensable to an adjustment for any increase cost caused by delay. According to [69] a delay is compensable to the contractor when it is caused by the owner, giving example of an incomplete drawing and specification, changes in scope or late possession of site, in which the conditions of contract allow the contractor to be entitled to a time extension, and to monetary recompense for extra costs caused by the delay.
Critical Delay; As per [63] these are delay claims that affect the progress, time and compensation. Non critical delays do not affect the completion date of the project. They affect the succeeding activities that are not on the critical path of the schedule. This can set back activities if they do not a float in the schedule.

2.4. Causes of Delay and Cost Overruns

Given the fact that; delay and cost overruns are a global problem in all building construction industry, as per [71] its causes whether due to cost estimation errors or any other reasons, still differs from one country to another depending on the political, economic and cultural reasons, [66]. Besides, delay and cost overruns may lead to an abandonment or termination of a building construction project, [22], if the causes are not well mitigated. Voluminous studies have been conducted to identify the causes of delay and cost overrun in building construction projects, as summarized in Table 2.1.
Table 2.1. Summary of causes of delays and cost overrun as retrieved from different literature review
     

2.5. Mitigation Measures for Controlling Delays and Cost Overrun

Building construction project delays and cost overruns, have been a major setback in the last decades, especially in developing countries. This is due to the fact that; keeping building construction projects within estimated costs and schedules, requires sound strategies, good practices, and careful judgment. Moreover, [22] asserts that; there are steps which can be taken to minimize their causes and effects of delay and cost overrun, as long as they are identified, and countermeasures are taken. These can be summarized as shown in Table 2.2, which show the mitigation measures on dealing with delays and cost overruns in building construction project.
Table 2.2. Summary of mitigation measure against delays and cost overrun as retrieved from different literature review
     

3. Methodology

The methodology and research design used in this study was case study survey, in which apart from literature review; instruments like questionnaire and interview were used by approaching various consultants, local building contractors registered under Class I to Class II, and their workers. The unit of analysis based on the public building projects in Dar-Es-Salaam, Tanzania. The case study was employed because it can bring an understanding of a complex issue or object, and extend experience or add strength to what is already known through previous research, and it emphasize detailed contextual analysis of a limited number of events or conditions and their relationships. Also, the study used both qualitative and quantitative approach, which made it easier in determining the intended objectives, samples and design of the study, as well as ranking the factor causing delay and cost overrun in building projects.

3.1. Data Collection Methods

Generally, both primary and secondary data collection, were done using multiple sources of evidence. Questionnaire survey was used to collect primary data from CRB, client, consultants, and local building contractors, in which the respondents answered the questions on their own, [72]. Some of the questions were close ended and others were open ended to the respondent to attest their own opinion, and give more information. Furthermore, secondary data concerning the influencing causes and mitigation measures of delays and cost overruns in building construction projects, were collected from literature review via published and unpublished books, journals, articles and papers. Literature was reviewed to determine the meaning of Delay and Cost Overruns; Types of Delay or Time Overrun; Causes of Delay or Time and Cost Overrun; and Mitigation Measures for Controlling Delays and Cost Overrun. All respondents had different years of experience in the construction industry.

3.2. Questionnaire Design

In this study, the questionnaires were prepared in accordance with objectives of the research. The questionnaire was divided into two parts which covered for both client, consultants, and building contractors; first part requested on general information about respondent, second part covered the possible mitigation measures in dealing with delays and cost overrun in building construction projects. Through a quantitative approach, data used were acquired with a questionnaire survey, in which the closed ended questionnaire was compiled based on the refined list above, after a pilot study. Closed-ended questions were used as they are very convenient for collecting factual data and are simpler to analyze because the range of potential answers is limited, [4]. However, open ended questions were also incorporated to get further opinions from respondents. The pilot study was carried out to mark better the quality of the questionnaire and improve reliability of the questions. Through using 5-point likert scale, and by using [39] writings in scaling; the respondents (clients, building contractors and consultants) were asked to respond to each statements, by indicating which statement is Very Important(VI)=5; Important(I)=4; Moderate(M)=3; Unimportant(U)=2; and Very Unimportant(VU)=1, so as to identify possible mitigation measures in dealing with the delays and cost overrun in building construction projects. This type of scale has been found to be acceptable in other construction management research.

3.3. The Study Sample and Population

[42] defines population as the entire mass of observations, which is the parent group from which a sample is to be formed. Additionally, [39] affirms that; this is a group of individuals, objects or items from which the sample is taken for measurement, and it refers to an entire group of person or elements which have one thing in common. In this study, the sample population includes building Contractors from class I – II, registered by CRB, consultants, and clients. The study employed both probability and non-probability sampling. Depending on the nature of respondents, different sampling technique were used:
§ For the building contractor’s population, stratified probability sampling was used, with the rationale behind the technique being the heterogeneity of the building contractor’s population in Tanzania, which is categorized into strata such as class I – VII. [42] insists that; the technique is precise, and it includes all important subpopulation; it is free from bias, and it ensures a sample that accurately reflects the population being studied.
§ For the client population, Purposive non-probability sampling was used. The rationale behind the technique is, as per [47] that; the client population undertaking building project is infinite, hence the personal judgment should be used.
§ For the consultant population, systematic probability sampling was used, the rationale being as per [47] that; the consultant population is large and homogeneous.
Furthermore, the sample size is proposed to determine what is termed by [39] as precision rate of and confidence rate. The size of sample should be optimum, neither large nor small. Strata sample size are determined by writings by [39] that;
Where: n = the sample size
N = the total number of population
Z = the confidence level
e = the margin/sampling error
p = the degree variability, which is 50%
q = 1- p.
Data used in sampling are confidence level (Z) - 95% (1.96) and margin/sampling error (e) - 5%. A study by [37, 51] shows that; these values are economical to be used and they have been used in various studies, including theirs.
For the Building Contractors
§ Class I
§ Class II
Table 3.1. The number of sample size from each of the local building contractors in Dar-Es-Salaam and distributed questionnaire
     
From the Table 3.1; the total proposed sample size selected is 39 local building contractors from class I and II, in Dar-Es-Salaam. The rationale behind selecting class I and II, is as per [42] writings that; delays and cost overrun are most common and frequent problem in large building projects, which most of them are undertaken by Class I and II.
For the Building Consultants
The population of consulting firm includes Quantity Surveying, Architectural and Engineering Firms, in which this study will concentrate more on a large number of Quantity Surveying Firms and few Architectural and Engineering Firms. There are 102 registered local Quantity Surveying firms in Dar-Es-Salam, i.e. N = 102. By applying the same formula by [39] in determining the sample size using confidence level:-
Systematic sampling procedure;- the sampling starts by selecting an element from the list at random and every kth element in the frame is selected, where k= the sampling interval (sometimes known as skip),
Where "N" is the population size and "n" is the sample size
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102.
For architectural and engineering firms, a sample of 6 firms was taken.
For the Client or Project Financier
The number of sample size for client through purposive sampling was 6. Finally; the total proposed sample size i.e. (building contractors, consultants and clients) is 79.

4. Results, Analysis and Discussion

Main parameters used for investigation in this study was the identification of mitigation measures in dealing with the delays and cost overrun in public building construction projects. Data were collected, analyzed and presented using Microsoft Word and Excel (Tables) in order to get more accurate computation that mapped out a pattern or relationship between measured or comparable variables. The study adopted the use of quantitative analysis method by using syntax mathematical operation in determining the mean score,
§ Mean Score Value =
Where: F = Frequency of response for each score
S = Score given each cause
N = The total number of respondent for each factor
Table 4.1. Mean score values (M) comparison table
     

4.1. Population Characteristics

This part mainly designed to provide general information about the respondents in terms of category of the organization, type of work executed, designation, experience, age and gender.
4.1.1. Age Distribution
Age is the critical factor in analyzing delay and cost overrun in building construction projects, because different parties with different age, has different approach in construction project. In this study the respondents age distribution, is as shown in Table 4.2.
Table 4.2. The Age of respondents
     
4.1.2. The Gender Distribution
The gender was also an important factor considered, as it constitutes other responsibilities apart from professional, which affect quality and commitments to project implementation, as shown in Table 4.3.
Table 4.3. The gender distribution
     
4.1.3. Category of Organization
The category of the respondent in the construction was another important factor considered, in order to obtain views from parties undertaking building projects in Dar-Es-Salaam, as seen in Table 4.4.
Table 4.4. The categories of respondents
     
Furthermore, building contractors of Class I and II were selected, as seen in Table 4.5.
Table 4.5. The categories of building contractors
     
Likewise, client can be either public or private. Due to the study nature, public developers were selected, due to their knowledge on building construction industry. Furthermore, consultants were categorized into Quantity Surveying, Architectural and Engineering consulting firm as shown below.
Table 4.6. The category of consultant
     
4.1.4. Type of Work Executed by the Respondents
The building construction projects executed and considered in this study are of different categories, which includes Residential, Commercial, Offices, Hospitals, Schools, etc.
4.1.5. Respondents Designation
There are various designations in construction industry which includes Quantity Surveyors, Architects, Engineers, Project Managers, Site Manager etc.
Table 4.7. The respondent designation
     
4.1.6. Experience of the Respondents
The respondents experience in relation to building construction project was a major factor to be considered in this study as seen in Table 4.8.
Table 4.8. Experience of the respondents
     

4.2. Possible Mitigation Measures in Dealing with the Delay and Cost Overrun in Building Projects

4.2.1. The Client or Project Financier’s Perspective
Where by TNR = Total Number of Response, and M.S = Mean Score.
Table 4.9 indicates that; Control design change was very important mitigation measure in dealing with the delays and cost overrun. Other mitigation measure were Plan a time schedule for material delivery process; Effective planning and scheduling, Comprehensive contract administration; Comprehensive contract administration; Accurate cost estimate; Adopt effective and efficient material procurement; Appoint competent site and project manager; Developed strategy for solving identified risk; Owners are recommended to review and improve bid document and Quickly informed the relevant parties when unforeseen circumstances affect the programme having mean score greater than 4.5.
Table 4.9. Possible mitigation measures in dealing with delay and cost overrun in building project – The Client or Project Financier’s Perspective
     
4.2.2. The Building Consultant’s Perspective
Where by TNR = Total Number of Response, and M.S = Mean Score.
Table 4.10 point out that; effective coordination and communication was very important mitigation measure in dealing with delays and cost overrun. The other mitigation measure includes prompt progress payment from payment having mean score greater than 4.
Table 4.10. Possible mitigation measures in dealing with delay and cost overrun in building project – The Building Consultant’s Perspectives
     
4.2.3. The Building Contractor’s Perspective
Where by TNR = Total Number of Response, and M.S = Mean Score.
Table 4.11 enlightens that; effective planning and scheduling was very important mitigation measure in dealing with delays and cost overrun having mean score 4.89. Other mitigation measure were comprehensive contract administration; accurate cost estimate; control change; prompt progress from client; quickly informed the relevant parties when unforeseen circumstances affect the programme; appoint competent site and project manager; make sure the timely availability of finance; effective coordination and communication; adopt effective and efficient material procurement; ensuring prompt resolution in designing change queries; issues and authorization report and hire competent labour having mean score greater than 4.
Table 4.11. Possible mitigation measures in dealing with delay and cost overrun in building project – The Building Contractor’s Perspectives
     
4.2.4. General Response
Where by TNR = Total Number of Response, and M.S = Mean Score.
Table 4.12, effective planning and scheduling was very important mitigation measure in dealing with delays and cost overrun having mean score 4.38. Other mitigation measures were control design change; Effective coordination and communication; Prompt progress payment from payment; Accurate cost estimate; Appoint competent site and project manager; Comprehensive contract administration; Ensuring prompt resolution in design change queries; issues and authorization report; Plan a time schedule for material delivery process; and Adopt effective and efficient material procurement.
Table 4.12. Possible measures in dealing with delay and cost overrun in building project – The General Perspective
     
Furthermore, respondents suggested other mitigation measure, which includes; design competition instead of quality cost based procurement; searching of the contractors as per the recent work done i.e. due diligence; selecting consultants and contractors via design competition; and understating client’s budget; participatory approach (which may include; donor, users, caretaker/estate office, consultants, contractors) during design and project execution. Also, respondents propose on; the type of contract format in relation to the nature and complexity of the building project, giving an example of FIDIC format used in design and built project. Most respondents, insisted on the government agencies in charge of issuing different building permits (e.g. local government agencies and national environmental management councils, NEMC) working together as a team, in order to reduce bureaucracy. They also enlightened on the agreed mode of handling queries on site before official approval, as well as consultants minimizing the use of imported foreign materials whenever necessary.

5. Discussion

Effective Planning and Scheduling: was ranked first with mean score 4.38, as seen in Table 4.12 whereby, in general 66% of the respondent considered this as the very important mitigation measure, while 17% of the respondent considered this as important, 11% considered as the factor as moderate and 24% of the respondent considered as unimportant. The important of this measure, is even emphasized by [9, 22, 34, 52] who insists on proper and project planning, and scheduling in mitigating delay and cost overruns. They narrate that; contractors should appoint project manager, who are expected to draw up a workable project plan, and strategies which should implement the project activities in the proper sequence, to complete the defined stages of the project within the stipulated time frame, with designated resources. [66] asserts on improving the ability of managers and engineers which may mitigate delay and cost overrun as they reduce the human and management problems. Furthermore, [40, 66] also insists on performing appropriate and proper preconstruction planning on tasks and resources, which may help on monitoring the project progress against stipulated time and budget. A faulty planning and scheduling may lead to delays and cost overrun e.g. due to poor site management and supervision; hence leading to the misunderstanding between owner, consultant and building contractors, [5].
Controlling Design Changes: was ranked second with mean score 4.36, as seen in Table 4.12 whereby, in general 60% of the respondent considered this as the very important mitigation measure, while 26% of the respondent considered this as important, 9% considered as the factor as moderate and 4% of the respondent considered as unimportant. This can be achieved by selecting a competent and reliable building consultant team and contractor team, which prepares appropriates standard drawings at the early construction stage, that are reviewed, and amended several times, for construction work, [8, 40, 66]. This concurs with [65] writings that; designs have high level of influence on the estimated project cost, and sometimes unsatisfactory design performance can lead to cost and time overrun. [66] suggests the need for project owners, architects and the design team, to work together to complete the design drawings, before project estimates are prepared or contracts are awarded in order to prevent inaccurate project estimates design changes, delay and cost overruns subsequently.
Effective Coordination and Communication Between Parties: was ranked third with mean score 4.30, as seen in Table 4.12 whereby, in general 53% of the respondent considered this as the very important mitigation measure, while 32% of the respondent considered this as important, 9% considered as the factor as moderate, 4% of the respondent considered as unimportant and 2% considered as very unimportant. Project issues or contractor request should be addressed timeously and information should be effectively managed. There must be a good communication management plan in place which take into account the agreed mode, hierarchy and channel, so as the site information is properly channeled and coordinated. In that way, most of delays and cost overrun in building project resulted by the slowness in giving instruction specifically from the architect, as part of the communication breakdown, as per [42, 56] can be avoided.
Prompt Progressively Payment from Client: was ranked third with mean score 4.30, as seen in Table 4.12 whereby, in generally 51% of the respondent considered this as the very important mitigation measure, while 34% of the respondent considered this as important, 11% considered as the factor as moderate, 2% of the respondent considered as unimportant and 2% considered as very unimportant. The agreed milestones for payment should be followed, alongside following the cash flow projection in project implementation plan, hence avoiding [3, 5, 8] writings that; building contractors cash flow problems, naturally affect the project’s completion.
Accurate Cost Estimates: was ranked fifth with mean score 4.28, as seen in Table 4.12 whereby, in general 60% of the respondent considered this as the very important mitigation measure, while 23% of the respondent considered this as important, 6% considered as the factor as moderate and 6% of the respondent considered as unimportant. Having accurate cost estimates,
Appointment of Competent Site and Project Manager: was ranked sixth with mean score 4.26, as seen in Table 4.12 whereby, in general 55% of the respondent considered this as the very important mitigation measure, while 28% of the respondent considered this as important, 9% considered as the factor as moderate and 4% of the respondent considered as unimportant.
Comprehensive Contract Administration: was ranked seventh with mean score 4.21, as seen in Table 4.12 whereby, in general 55% of the respondent considered this as the very important mitigation measure, while 23% of the respondent considered this as important, 13% considered as the factor as moderate, 4% of the respondent considered as unimportant and 4% considered as very unimportant. Most of the projects have consultant as project manager, who liaise between client and contractor, in making sure that the contract is administered compressively,[9]. The required management principle should be utilized during project execution to mitigate delays and cost overrun.
Ensuring Prompt Resolution in Design Change Queries, Issues and Authorization Report: was ranked eighth with mean score 4.17, as seen in Table 4.12 whereby, in general 43% of the respondent considered this as the very important mitigation measure, while 40% of the respondent considered this as important, 10% considered as the factor as moderate, 5% of the respondent considered as unimportant and 2% considered as very unimportant. When queries are observed in the design, construction ceases until the query is resolved. This stalls the construction process leading to delay in completing the project. Thus, queries should be promptly resolved, and consultant should promptly resolve all the quarries in the design to ensure smoothly progress of work. [8, 56] asserts that; projects are required to be completed on schedule, within budget and according to the specification; if the consultant does not identify errors and omission in the design or bill of quantity early enough, lead to delay and cost overrun, which can be resolved by having prompt resolution.
Adopt Effective and Efficient Planning Time Schedule for Material Procurement and Delivery Process: was ranked ninth with mean score 4.11, as seen in Table 4.12 whereby, in general 49% of the respondent considered this as the very important mitigation measure, while 21% of the respondent considered this as important, 21% considered as the factor as moderate, 4% of the respondent considered as unimportant and 4% considered as very unimportant. [26] affirms that; responsible party should have early procurement plan to ensure building materials are available on-site when needed. Responsible party should plan a time schedule for material delivery process to ensure the availability of material when needed, in order to avoid delay and cost overrun.
Ensuring on the Timely Availability of Finance: was ranked twelfth with mean score 4.02, as seen in Table 4.12 whereby, in general 17% of the respondent considered this as the factors very important, while 51% of the respondent considered this as important, 26% considered as the factor as moderate, 2% of the respondent considered as unimportant and 4% considered as very unimportant. Even [40, 66] insists on ensuring that funds are adequately released during relevant phases of projects execution. Milestones payment should be made on time due to organizational lapses or bureaucracy.
Other possible mitigation measures in dealing with delay and cost overrun in public building project, as suggested by the respondents includes: - frequent progress management meeting; consistent supervision, site and technical meetings; frequent coordination between the parties involved; use of up-to-date technology and construction methods; clear information and communication channel among project team members; and delay in decision making. Clients are the project owner, when they do not make decisions on time regarding project matters, they slow down on site project activities. This compliments [23] writings that; slow decision making could be caused by an organization’s internal bureaucracy, or wrong channel of communication in building projects.

6. Conclusions

This study identified mitigation measures in dealing with delay and cost overrun in public building project, in which out of 25 mitigation measures, effective project planning and scheduling was ranked first; followed by controlling design changes, and effective coordination and communication between parties. Furthermore, the respondents insisted on more attention to be paid on the progressively payment to the parties by the client; having accurate cost estimates; as well as appointment of competent site and project manager. Other included, comprehensive contract administration; ensuring prompt resolution in design change queries, issues and authorization report; efficient and effective planning time schedule for material procurement delivery process; developing effective strategic planning for solving identified risks; and ensuring on the timely availability of finance.

References

[1]  Alaghbari, M, Razali, A, Salim, A. & Ernawati, E (2007); The Significant Factors Causing in Delay of Building Construction Projects Malaysia, In The Journal of Engineering, Construction and Architectural Management, Vol. 05(05); 12 - 15.
[2]  Al-Keim, A., (2017); “Strategies to Reduce Cost Overruns and Schedule Delays in Construction Projects”, Published Ph.D Dissertation, Doctor of Business Administration, College of Management and Technology, Walden University, Walden Dissertations and Doctoral Studies Collection, 145 Pages.
[3]  Albogamy, A., Scott, D., & Dawood, N., (2013); “Dilemma of Saudi Arabian Construction Industry”, in the KICEM Journal of Construction Engineering and Project Management, Vol.03(04), 35 - 40.
[4]  Alinaitwe, H. & Ayesiga, R. (2013); Success Factors for the Implementation of Public Private Partnerships in the Construction Industry in Uganda. In the Journal of Construction in Developing Countries. Vol.18(02), 01 - 14.
[5]  Alzara, M., Kashiwagi, J., Kashiwagi, D., Al-Tassan, A., (2016); “Using PIPS to Minimize Causes of Delay in Saudi Arabian Construction Projects: University Case Study”, in the Procedia Engineering, the International Conference on Sustainable Design, Engineering and Construction, Published by ELSEVIER, Science Direct, Peer-review under responsibility of the organizing committee of ICSDEC 2016, Page 932-939, (doi:10.1016/j.proeng.2016.04.121).
[6]  Amandin, M.M, & Kule, J.M, (2016); Project Delays on Cost Overrun Risks: A Study of Gasabo District Construction Projects in Kigali, Rwanda; In the Journal of Advanced Research, Vol.(05)(01).
[7]  Ameh, O, Soyingbe, A & Odusami, K.T, (2010); Significant Factors Causing Cost Overruns in Telecommunication Projects in Nigeria, In the Journal of Construction in Developing Countries, Vol. (15)(02), 49 - 67.
[8]  Assaf, S.A. & Al- Hejji, S. (2006); Causes of Delays in Large Construction Projects, In the International Journal of Project Management, Vol.(24)(04), 349 - 357.
[9]  Awolesi, J.A.B., Fabi, J.K., & Akinseinde, O.A., (2015); “Assessment of Contractors’ Mitigating Measures for Cost Overrun of Building Projects in South-Western Nigeria”, in the Journal of Sustainable Development, Vol.(08)(09), ISSN 1913-9063; E-ISSN1913-9071, Published by Canadian Center of Science & Education (DOI:10.5539/jsd.v8n9p139) (URL: http://dx.doi.org/10.5539/jsd.v8n9p139).
[10]  Azhar, N, Rizwan, U, Farouqui, F. & Ahmed, S. (2008); Cost Overrun Factors in Construction Industry of Pakistan; Advancing and Integrating Construction Education Research & Practice, 499 - 508.
[11]  Aziz, R. (2013); Factors Causing Cost Variation for Constructing Wastewater Projects in Egypt, In The Alexandria Engineering Journal, Vol.(52)(01), 51 - 66.
[12]  Bentil, E, Addy, E.N, Asare, E.K & Fokou-kusi, A. (2017); The Level of Existence and Impact of Cost and Time overrun in Building Construction Project in Ghana, In The Journal of Civil and Environmental, Vol.(22)(01), 21 - 36.
[13]  Bitomwa, H (2013); Evaluation of the Causes of Project Cost Overrun Within the Tanzania Construction Sector, Unpublished Undergraduate Dissertation, Department of Building Economics, ARDHI University(ARU), Dar-Es-Salaam, United Republic of Tanzania.
[14]  Braimah, N. (2008); Understanding Construction Delay Analysis and the Role of Preconstruction Programming, In the Journal of Management in Engineering, Vol.(04)(06), 25 - 44.
[15]  Bramble, B. & Callahan, M. (1987); Construction Delay Claims, Published by John Wiley & Sons, Inc., USA.
[16]  Chan, D, Chan, A, Lam, T. & Chan, H. (2010); Exploring the Key Risks and Risk Mitigation Measures for Guaranteed Maximum Price and Target Cost Contracts in Construction, In the Journal of Construction Law Journal, Vol.(26)(05), 364 - 378.
[17]  Chitkara, K.K. (2011); Construction Project Management, Planning, Scheduling and Controlling, 2nd Edition, Published by McGraw Hills.
[18]  Chidambaram, R., & Potty, N.S., (2014); “Qualitative Analysis of Time Delay and Cost Overrun in Multiple Design and Build Projects”, A Paper Presented During the International Conference Data Mining, Civil and Mechanical Engineering (ICDMCME) February 04-05, 2014, Bali, Indonesia, (http://dx.doi.org/10.15242/IIE.E0214003).
[19]  Cunningham, T., (2017); “What Causes Cost Overruns on Building Projects? - An Overview”, School of Surveying and Construction Management, Dublin Institute of Technology, 28 Pages, (https://arrow.dit.ie/cgi/viewcontent.cgi?article=10 70&context=beschreoth).
[20]  Danso, H. & Antwi, J. (2012); Evaluation of the Factors Influencing Time and Cost Overruns in Telecom Tower Construction in Ghana, In the Journal of Civil and Environmental Research, Vol.(02)(06), 15 - 24.
[21]  Doloi, H. (2011); Understanding Stakeholders' Perspective of Cost Estimation in Project Management, In The International Journal of Project Management, Vol.(29)(05), 622 - 636.
[22]  Dolage, D.A.R., & Pathmarajah, T (2015); “Mitigation of Delays Attributable to the Contractors in the Construction Industry of Sri Lanka - Consultants’ Perspective”, in the Journal of Engineer, Vol.(08)(01), 21 - 30, Published by the Institution of Engineers.
[23]  Doran, T, Mansfield, N.R & Ugwu, O.O, (1994); Causes of Delays and Cost Overrun 4in Nigerian Construction Projects, In the International Journal of Project Management, Vol.(12)(04), 254 - 260.
[24]  Enshassi, A, Al-Najjar, J, & Kumaraswamy, M. (2009a); Delays and Cost Overruns in the Construction Projects in the Gaza Strip, In the Journal of Financial Management of Property and Construction, Vol.(14)(02), 126 - 151.
[25]  Flyvbjerg, B. (2005); Policy and Planning of Large Infrastructure Project Problems, Causes, Cures, World Bank Policy Research Working Paper 3781.
[26]  Frimpong, Y, Oluwoye, J. & Crawford, L. (2003); Causes of Delay and Cost Overruns in Construction of Groundwater Projects in a Developing Countries; Ghana as a Case Study, In the International Journal of Project Management, Vol.(21)(05), 321 - 326.
[27]  Gahtan, H. & Mohan, S. (2007); Investigation of Significant Factors Influencing Time and Cost Overrun in Building Projects, In the Civil and Environmental Research, Vol.(12)(16), 25 - 44.
[28]  Gunduz, M., Nielsen, Y. & Özdemir, M. (2013); Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey, In the Journal of Management in Engineering, Vol.(29)(02), 133 - 139.
[29]  Heravi, G., & Mohammadian, M., (2017); “Cost Overruns and Delay in Municipal Construction Project in Developing Countries”, In the AUT Journal of Civil Engineering, Vol.(01)(01), 31 - 38 (DOI: 10.22060/ceej.2017.12189.5163).
[30]  Hwang, B.O., & Yang, S., (2014); “Rework and Schedule Performance; A Profile of Incidence, Impact, Causes and Solutions”, in the Journal of Engineering, Construction and Architectural Management, Vol.(21)(02), 190 - 205, Published by Emerald Group Publishing Limited, (DOI:10.1108/ECAM-10-2012-0101).
[31]  Ijigah, E.A, Ogunbode, E.E. & Ibrahim, M.O. (2012); Analysis and Prediction of Cost and Time Overrun of Millennium Development Goals (MDGS) Construction Project in Nigeria, In the International Journal and Books Hosting, Vol.(02)(10).
[32]  Iyer, K, Chaphalkar, N. & Joshi, G.A. (2007); Understanding Time Delay Disputes in Construction Contracts, In the International Journal of Project Management, Vol.(26)(02), 174 - 184.
[33]  Jeykanthan J, & Jayawardena A.K.W, (2012); Mitigating Delays in Donor Funded Projects in Sri Lanka, In the KSCE Journal of Civil Engineering, Vol.(22)(16), 221 - 234.
[34]  Kaliba, C, Muya, M, & Mumba, K. (2009); Cost Escalation and Schedule Delays in Road Construction Projects in Zambia, In the International Journal of Project Management, Vol. (02)(05), 522 - 531.
[35]  Kamaruzzaman, S. & Ali, A. (2010), Cost Performance for Building Construction Projects in Klang Valley, In the Journal of Building Performance, Vol.(01)(01), 110 - 118.
[36]  Kesavan, M., Gobidan, N.N., & Dissanayake, P.B.G., (2015); “Planning & Mitigation Methods to Reduce the Project Delays in Sri Lankan Civil Engineering Construction Industries”, A Paper Presented During the 6th International Conference on Structural Engineering and Construction Management, (ICSECM), Kandy, Sri Lanka, 11th – 13th December, 2015, Page 102 to 107.
[37]  Kihaule, A. (2011); Analysis of Determinants of Rural Households Purchase of Micro Health Insurance Plans in Tanzania. Nairobi, Research Proposal Approved and Funded by the African Economic Research Consortium (AERC).
[38]  Kikwasi, G. (2012); Causes and Effect of Delays and Disruption in Construction Project in Tanzania, In The Australasian Journal of Construction Economics and Building. Conference Series I, Issue (02), 52 - 59.
[39]  Kothari, C.R, (2004); Research Methodology: Methods and Techniques, 2nd Revised Edition, New Age International (P) Limited Publishers, New Delhi, India.
[40]  Koushki, P, Al‐Rashid, K. & Kartam, N. (2007); Delays and Cost Increases in the Construction of Private Residential Projects in Kuwait, In the Journal of Construction Management and Economics, Vol.(23)(03), 285 - 294.
[41]  Kumaraswamy, M. M. & Chan, D.W.N. (1998); Contributors to Construction Delays in Indonesia, In the Journal of Construction Management and Economics, Vol.(16), 17 - 29.
[42]  Kyando, R. (2013); “Magnitude of Time and Cost Overruns in Building Projects”, Unpublished Undergraduate Dissertation, Department of Building Economics, Ardhi University(ARU), Dar-Es-Salaam, Tanzania.
[43]  Leeman, T. (2007); Project Management: Managing the Chaos of Change, In the Journal of Business Strategy, Vol.(23)(05), Page 5.
[44]  Le-Hoai, L, Lee, Y.D. and Lee, J.Y. (2008); Delay and Cost Overrun in Vietnam Large Construction Projects: A Comparison with Other Selected Countries, In the KSCE Journal of Civil Engineering, Vol.(12)(06), 367 - 377.
[45]  Lester, A. (2000); Project Planning and Control. Published by Butterworth Heinemann, Oxford, United Kingdom (U.K).
[46]  Luvara G.M.V., Phoya, S., Tesha, D.N.G.A.K., & Lyimo K.S., (2018); “Critical Factors Causing Delay and Cost Overrun in Public Building Projects in Dar-Es-Salaam, Tanzania”, in the PARIPEX - Indian Journal of Research, Vol.(07)(07), 11 - 16, ISSN-2250-1991, (https://www.worldwidejournals.com/paripex/file.php?val=July_2018_1530787910__84.pdf).
[47]  Luvara G.M.V. & Mwemezi B.R., (2017); “Obstacles against Value Management Practice in Building Projects of Dar es Salaam Tanzania”, in the International Journal of Construction Engineering and Management, Vol.(06)(01), 13 - 21, Published by Scientific & Academic Publishing, p-ISSN:2326-1080; e-ISSN:2326-1102, (DOI:10.5923/j.ijcem. 20170601.02).
[48]  Mahamid, I. & Dmaidi, N. (2013); Risks Leading to Cost Overrun in Building Construction from Consultants’ Perspective, Organization, Technology and Management in Construction, Vol.(05)(02), 860 - 873.
[49]  Marzouk, M.M. & El-Rasas, T.I. (2014); Analyzing Delay Causes in Egyptian Construction Projects, In the Journal of Advanced Research, Vol.(05)(01), 49 - 55.
[50]  McCord, J., McCord, M., Davis, P.T., Haran, M., & Rodgers, W.J., (2015); “Understanding Delays in Housing Construction: Evidence from Northern Ireland”, In the Journal of Financial Management of Property and Construction, Vol.(20)(03), 286 - 319 Published by Emerald Group Publishing Limited, (DOI:10.1108/JFMPC-07-2015 -0028).
[51]  Mchome, E.E, (2014); Development of a Model for Improvement of Transport Network in Informal Settlements in Dar-Es-Salaam, Tanzania, PhD Thesis, University of Dar-Es-Salaam (UDSM), Dar-Es-Salaam, Tanzania.
[52]  Memon, A.H, Rahman, I.A. & Azis, A.A.A. (2013a); Assessing Causal Relationships Between Construction Resources and Cost Overrun Using PLS Path Modeling Focusing in Southern and Central Region of Malaysia Material Resource, In the Journal of Engineering and Technology, Vol.(04)(01), 67 - 77.
[53]  Memon, A.H., Rahman, I.A. & Azis, A.A.A. (2011); “Preliminary Study on Causative Factors Leading to Construction Cost Overrun”, in the International Journal of Sustainable Construction Engineering & Technology, Vol.(02)(01).
[54]  Mtallib, M.O.A. (2007); Evaluation of the Relationship Between Delayed Payments and Cost and Time Overruns, Unpublished Masters Dissertation, Department of Building Faculty of Environmental Design, Nigeria, Ahmadu Bello University.
[55]  Mukuka, M.J. (2015); Cost and Schedule Overrun in Construction Project in South Africa, Unpublished Master Thesis, M.Tech. (Construction Management), University of Johannesburg, Johannesburg, South Africa, 147 Pages (https://0x9.me/k7meB).
[56]  Naveenkumar, G.V. & Prabhu, V. (2016); Factors Influencing Time and Cost Overruns in Construction Projects, In the International Journal of Innovative Research in Science, Engineering and Technology.
[57]  Nawaz, T, Shareef, N.A. & Ikram, A.A. (2013); Cost Performance in Construction Industry of Pakistan, In the Journal of Industrial Engineering Letters Vol.(03)(02), 19-33.
[58]  Nicholas, J. (2001); Project Management for Business and Technology. Published By Prentice Hall, New Jersey, USA.
[59]  Olawale, Y. & Sun, M. (2010); Cost and Time Control of Construction Projects: Inhibiting Factors and Mitigating Measures in Practice, In the Journal of Construction Management and Economics, Vol.(28)(05), 509 - 526.
[60]  Pai, S.K. & Bharath, J.R. (2013); Analysis of Critical Causes of Delays in Indian Infrastructure Projects, In the International Journal of Innovative Research and Development, Vol.(02)(03), 251 - 263.
[61]  Pallangyo, M. (2013); Assessment of the Causes and Effect of Cost Overrun in Building Construction, Unpublished Undergraduate Dissertation, Department of Building Economics, Dar-Es- Salaam, ARDHI University(ARU), Dar-Es-Salaam, Tanzania.
[62]  Polat, G., Okay, F., & Eray, E., (2014); “Factors Affecting Cost Overruns in Micro-scaled Construction Companies”, in the Procedia Engineering, Vol.(85), 428 - 435, Published by Science Direct, ELSEVIER, (DOI:10.1016/j.proeng.2014.10 .569).
[63]  Rahman, A, Berawi, H, Berawi, M.A, Mohammed, A.R, Othman, M. & Yahya, I. A. (2006); Delay Mitigation in the Malaysian Construction Industry, In the Journal of Construction Engineering and Management, Vol.(132)(02), 125 - 133.
[64]  Rahman, I.A, Memon, A.H. & Karim, A.T. (2013); Significant Factors Causing Delays and Cost Overrun in Large Construction Projects in Malaysia, In the Journal of Applied Science, Vol.(13)(02), 286 - 293.
[65]  Rajakumar, A.C. (2016); Analysis of Cost Overrun in Road Construction Activities – A Critical Review, In the International Research Journal of Engineering and Technology, Vol.(03), e-ISSN 2395-0056.
[66]  Ramabhadran, M., (2018); “An Investigation into Cost Overrun in Construction Projects in United Arab Emirates”, in the International Journal of Construction Engineering and Management, Vol.(07)(01), 01 - 21, Published by Scientific & Academic Pulishing, (DOI: 10.5923/j.ijcem.20180701.01).
[67]  Sambasivan, T. & Soon, W, (2006); Causes and Effect of Delays in Malaysian Construction Industry, In the Journal of Industrial Engineering Letters, Vol.(03)(02), 33 - 42.
[68]  Shibani, A., & Arumugam, K., (2015); “Avoiding Cost Overruns in Construction Projects in India”, in the Journal of Management Studies, Vol.(03),(07-08), 192 - 202, David Publishing, (DOI: 10.17265/2328-2185/2015.0708.003).
[69]  Srdic, A., & Selih, J., (2015); “Delays in Construction Projects: Causes and Mitigation,” In an International Journal of Organization, Technology and Management in Construction, Vol.(07)(03), 1383 - 1389.
[70]  Subramani, T, Sruthi, P.S. & Mkavitha, J. (2014); Causes of Cost Overrun in Construction, In the Journal of Engineering, Vol.(02)(02), 23 - 32.
[71]  Soliman, E., (2017); “Recommendations to Mitigate Delay Causes in Kuwait Construction Projects”, in the American Journal of Civil Engineering and Architecture, Vol.(05)(06), 253 - 262, Published by Science & Education Publishing (SciEP), (DOI:10.12691/ajcea-5-6-5).
[72]  Trueman, C. (2015); Structured Questionnaire, History of Learning Site, (https://0x9.me/P7QNF).