International Journal of Construction Engineering and Management

p-ISSN: 2326-1080    e-ISSN: 2326-1102

2017;  6(5): 209-214

doi:10.5923/j.ijcem.20170605.03

 

Assessment of Compensation for Delay Claims in Case of Partial Disruption in Work

Sridhar M.1, Kumar VSS2

1Ph.D. Student, Osmania University, Hyderabad, India

2Vice Chancellor, JNTU, Kakinada, A.P. India

Correspondence to: Sridhar M., Ph.D. Student, Osmania University, Hyderabad, India.

Email:

Copyright © 2017 Scientific & Academic Publishing. All Rights Reserved.

This work is licensed under the Creative Commons Attribution International License (CC BY).
http://creativecommons.org/licenses/by/4.0/

Abstract

Because of delays in project execution due to reasons attributable to project owners, the contractors lodge delay claims for prolongation of work. In case of partial disruption in work, the delay claims are framed by contractors based on actual work turnover achieved which methodology is challenged and disputed by project owners. The arbitrators while judging the fair compensation for delay claims in such cases make an assessment of reasonable turn over using their experience and subjective knowledge. The qualitative factors which influence the turnover have been identified for making an assessment of the turn over under given site specific conditions. For studying the influence of these qualitative factors structured interviews were conducted with the experts through questionnaires. The opinions gathered from the experts have been analysed following Fuzzy Delphi Methodology (FDM). The factors which have considerable and significant influence on the turnover have been listed. Based on the findings, a methodology is suggested for assessment of compensation for delay claims in these cases.

Keywords: Delay claims, Turn over, Overheads, Arbitrators, Expert opinions, Productivity

Cite this paper: Sridhar M., Kumar VSS, Assessment of Compensation for Delay Claims in Case of Partial Disruption in Work, International Journal of Construction Engineering and Management , Vol. 6 No. 5, 2017, pp. 209-214. doi: 10.5923/j.ijcem.20170605.03.

1. Introduction

Indian construction industry is riddled with many litigations pertaining to delay claims. Because of delays in project execution caused due to reasons attributable to project owners like delays in handing over work fronts, issue of drawings, delays in decisions, delayed payments and approvals etc., the contractors lodge claims seeking compensation for delays. Such delay claims are framed for the periods of delay as actual costs incurred under various heads which could not be recovered because of drop in productivity. Typically, the heads on which delay claims are framed include but not limited to the following.
1. Machinery and equipment
2. Manpower (Technical, non-technical labour)
3. Other resources deployed
4. Site Overheads
5. General office overheads
6. Head office overheads
7. Interest, Finance charges
8. Charges on Insurance, Bank Guarantees
9. Loss of Profit
The site / field office over heads for a particular project are easily assessable as they are project based with good records keeping and documentation of accounts. The head office overheads (HOOH) are not easily assessable as they are as a whole for head office and hence allocation of them to a single project is complex. There are numerous formulae available for assessing HOOH amongst which Hudson's formula, Emden’s formula and Eichleay formula are popular. The delay claims are lodged as compensation for the losses towards non-recovered costs incurred under various heads as above. The contractors do include such overheads and establishment costs in bids which are intended to be recovered from the work turn over that is monthly billing. When there is total disruption in work for certain periods, there will not be any work out turn. In such cases the quantification of claims is done as actual costs incurred under above heads for the periods of work disruption. Such claims are treated as compensation for losses by way of non recovery of costs incurred due to loss in productivity.
In many cases the disruption in work is only partial wherein only some portion of the work is hindered. In such cases the delay claims are framed based on lost productivity. The financial turnover as monthly billed value of the work is taken as a metric for productivity. Thus lost productivity is computed as the difference of originally planned turnover in the month to the turnover actually achieved. The ratio of lost productivity to the planned turnover is termed as underutilization factor. In cases of partial disruption in work, the delay claims are quantified by multiplying the costs incurred under various heads with this factor. The delay claims lodged by contractors with this methodology are often disputed by project owners. The project owners dispute the quantification arguing that the turn over achieved could be more citing contractor’s inefficiency. On the other hand the contractors argue that the turn over achieved is maximum possible under the given site conditions. The arbitrators as judges have challenging task in these cases in assessing the reasonable compensation for the delay claims using their subjective knowledge and expertise.
For assessing fair compensation for delay claims in cases of partial disruptions, the turn over that can be reasonably achieved under given site conditions needs to be assessed. The factors that influence the work turn over are qualitative in nature the effect of which can’t be easily quantified. Deterministic mathematical models are not suitable for solving such types of problems where fuzzy set theory and system modelling based on approximate reasoning are found useful. Further the modeling based on human perception and judgment offer solutions to such type of problems.

2. Research Methodology

Numerous studies are conducted on the delay causes and their prevalence, significance concerning project execution. Around thirty such delay causes/factors were shortlisted which have a bearing on the work turn over. From these about fifteen qualitative factors were identified by consulting the experts which influence the work out turn of contractor's resources and thereby the financial turnover. The factors do have varying influence which is qualitative in nature. These factors are categorized in to three distinct subheads. Those factors which are related to site are categorized as 'Site Constraints'. Again the factors which are influenced by Project owner are grouped in 'Owner Related issues' and the problems related to and specific to work execution are taken in 'Execution issues / Problems'
I. Site Constraints
1. Quantum of availability of fronts
2. Sequence interdependency of activities/ cycle of operations
3. Scatterness of available front locations
4. Shifting of site locations
5. Constraints on deployment of resources
II. Owner Related Issues
1. Drawings, decisions on hold
2. Delay in payments
3. Delays in sanctions, clearances and approvals
4. Non-resolution of issues in time
5. Local problems, issues
III. Execution issues/ Problems
1. Restrictions, constraints in execution (conditions, timings, weather)
2. Large scale variations/ deviations
3. Changes in methodology
4. Frequent disruption in work
5. Miscellaneous management issues, coordination
It is proposed to study the influence of the above qualitative factors by obtaining opinions from a group of experts who will judge such influence of these factors on work turn over using their subjective knowledge. Such opinions are to be collected from the experts by conducting structured interviews which opinions can be subjected to analysis applying Fuzzy Delphi methodology.

2.1. Structured Interviews

For studying the influence of these qualitative factors, about 20 experts have been selected who are experienced and involved in deciding the delay claims in arbitration tribunals as arbitrators. These senior persons as experts have experience in judging the issues and disputes related to delay claims using their subjective knowledge. It is proposed to collect the expert opinions from these experts through structured interviews by well-structured questionnaire. The Fifteen Qualitative factors are listed with a brief back ground and introduction of issue as a preamble. A brief note is given narrating the qualitative factors.
The structured interviews conducted for the experts opinions, consist two parts of questionnaire. In the first part the experts are asked to rate the importance of the listed qualitative factors on affecting the turnover, on a scale of 1 to 5 as shown below.
1. Very low important
2. Low important
3. Medium important
4. High important
5. Very high important
In the second part, the experts were asked to judge the effect of the qualitative factors on turnover in three opinions normal, minimum and maximum effect as they judge. First one is the normal, optimum effects which as experts feel most likely. Again the maximum and minimum effect of variables on the turnover as judged by the experts is asked. For judging the effect, semantic variable scale is provided as exhibited in Fig.1 for easy reference. Thus if the qualitative effect is judged “moderate" a score of 10 or if it is "severe” then a score 20 can be taken as given in scale. Accordingly, experts were asked to quantify the qualitative effect.
Figure 1. Semantic Scale
Such data gathered through structured interviews on the expert judgments as max, min and most presumptive effect quantified as three-time opinions are taken as Triangular Fuzzy numbers (T.F.N.s) for carrying out analysis by Fuzzy Delphi method (F.D.M.).

2.2. Fuzzy Delphi Method

In this method, the experts use their individual competency and subjectivity in estimating the effect of the fifteen qualitative factors on the turn over as a three time estimate. This is the very reason why the use of fuzzy concepts is proposed for application of Fuzzy Delphi Method. In Delphi method the experts opinions are subjected to statistical analysis for convergence but in Fuzzy Delphi method fuzzy concepts are used for convergence.
The three time estimates considered as T.F.N.s are taken as a sheaf for carrying out analysis of experts opinions.
The Steps in F.D.M are depicted as follows:
1. The sheaf of expert opinions is (A1(i), B1(i), C1(i)). Where i indicates the index attached to expert and 1 indicates this is first phase of the forecasting process.
2. These responses from 'n' experts form a sheaf
(Al(i), B l(i), Cl(i)), i=1,2,......n.
The mean of this T.F.N. sheaf is then computed (A1m, B1m, C1m)
3. For each expert the divergence is computed as follows
{A1m – A1(i), B1m – B1(i), C1m - C1(i)}
Where these divergence numbers can be positive, null or negative. This information is then sent to each individual expert.
4. Each Expert now gives a new T.F.N.
(A2(i), B2(i), C2(i)) and the process, starting with phase 2 is repeated.
5. A study of partial group opinions is realized using the distance between the T.F.N. and the decomposition of the dissemblance relations in the maximal sub-relations of similarity.
6. Distances and Grouping of similarities: The Normalized distances between two T.F.N.s are calculated with left and right distances taking two values.
7. The normalized distance between two T.F.N.s is given by
Ni,Nj are respective T.F.N.s given by experts i, j and ∆l,∆r is left and right distances. β2, β1 are arbitrary values at right and left respectively such that 0 ≤ δ ≤ 1.
8. Again for A = [a1, a2], B = [b1, b2]; ∆l (A,B) left distance = |a1, b1|
Right distance ∆r = | a2, b2|; For T.F.N.s it is (X1+ 2Y1+Z1) / 2
9. The distances between Fuzzy numbers and similarity of experts opinions with in a permissible range of δ (Ni,Nj) are to be assessed and grouped in matrix form. The similarity of group of experts opinions are also to be exhibited graphically.

3. Presentation of Results and Analysis

The experts opinions as a set of three numbers quantified as per semantic scale for each qualitative factor are taken as T.F.N.s for application of F.D.M. Thus for each of fifteen qualitative factors the sheaf of experts opinions are tabulated for carrying out analysis following the steps of F.D.M. For each qualitative factor the mean of T.F.N., Am and the divergence of expert opinions with mean are calculated and tabulated. The normalized distances between the experts opinions (T.F.N.s) are computed for each of qualitative factors as per F.D.M. The similarity of groupings of experts has been made with an allowable range in the form of matrix and tabulated along with graphical representations. Since there is good convergence observed with around 75% experts expressing similarity in opinions, repetition of process was not considered.
Based on the importance of the qualitative factors rated by experts, the Relative importance index R.I.I. values are calculated and tabulated in Table 3.1.
Relative Importance Index (R.I.I.) = ∑ W / A x N
For each variable (Say for variable i) W = W1 N1 + W2 N2 + W3N3 + …W5N5
W1, W2, W3, W5 are respective weightage of importance
N1, N2, N3, N4, N5 are No. of responses for respective importance factor.
For each of the fifteen qualitative factors the experts opinions as triplet were considered as T.F.N.s and tabulated for analysis. Each expert is given a code number. Based on the values of T.F.N.s tabulated, the mean of T.F.N.s are calculated for each of the qualitative factor, which are exhibited in Table 3.1 together with R.I.I. values. Based on R.I.I. values, the rank is also assigned as can be seen from Table 3.1. As can be seen from this table, for seven qualitative factors with ranks 9 to 15 the minimum and normal values of mean T.F.N.s are less than 5. Again the maximum T.F.N. value for these factors is in range of 5 to 10. From the semantic scale it indicates that the significance of these seven factors on turnover is less. Again for comparison, the R.I.I. value for these seven qualitative factors is less than 0.5. Thus among 15 qualitative factors, only for about eight factors the experts have opined that their effect is significant. Thus the eight qualitative factors which have significant effect on work turn over, are listed in Table 3.2. The influence of the factors by converting the mean T.F.N. value in to semantic scale are exhibited in Table 3.2. The mean of R.I.I. is calculated and the difference of RI.I. with the mean for each factor as variance is calculated and exhibited in this table.
Table 3.1. Mean T.F.N.S and Rankings for Factors
     
From the analysis of influence of factors based on semantic scale as exhibited in Table 3.2 and based on variance values indicated, for four factors at S.no.1,6,7,8 the effect is ‘less to moderate’. The remaining four qualitative factors have greater influence on turn over which are exhibited in Table 3.3. The factors are listed along with subsystems. Again based on the findings, among the four factors listed, the first two factors have even greater influence on the turn over. Based on the analysis, the suggested range of influence for the qualitative factors is given in Table 3.4. Based on the prevalence of the factor as minimum, normal or maximum for the particular case, the value from the range can be considered. Based on relative influence of these four factors the weightages of the factors out of 100 are worked out and exhibited in Table 3.4.
Table 3.2. Influence of Qualitative factors on Turn over
     
Table 3.3. Factors with significant influence
     
Table 3.4. Suggested ranges of influence of the factors
     
In light of the above, a methodology is suggested for assessing the compensation for a specific case. For a particular case based on the severity of the four factors listed in Table 3.4 judged as minimum, normal or severe prevailing at site, the value can be considered from the suggested ranges. This value from the range can be multiplied with the weightage of the factor specified in table 3.4 for computing the weighted average of for the four factors. This weighted average can be considered as underutilization factor as a reasonable assessment of the lost productivity for the particular case. The projected costs by the contractor under various heads claimed for compensation can be multiplied by this underutilization factor assessed, to arrive at a fair compensation for the claim.

4. Conclusions

For assessing a fair compensation in case of partial disruption in work, the arbitrators use their expertise, experience. While making the best judgment they keep in mind the influence of the qualitative factors prevailing at site for the particular instance of case.
From this study the factors that have significant and considerable effect on the turn over as a measure of productivity have been identified. The quantification of the qualitative effects of these factors on the turnover have been studied under given site circumstances. Based on the above findings, a methodology is suggested for quantifying the effect of the above qualitative factors. By assigning the relative weightage to the factors out of 100 and considering the severity of the variable / factor in a particular case, the methodology consists of computing weighted average to assess the underutilization factor as a measure of lost productivity. The fair compensation can be worked out based on this factor of underutilization so computed.
In this research work, an attempt has been made to convert the expertise, subjective analysis based on experience of experts into formal methodology. This is applicable to such cases only if the four qualitative factors listed in Table 3.4 have the influence of some scale. Otherwise the computation of weighted average gives misleading results.
The methodology is based on reasonable assessment following the subjectivity which can’t be compared with results proved by exactitude of deterministic mathematical models.

References

[1]  John Mendes., 1995, “Delay Claim: Measuring the impact”. Lesperance Mendes Lawyers, Vancouver B.C. V6Z2M4 web Journal accessed and downloaded.
[2]  Jonathan Jing Shengshi, S.O. Cheung and David Arditi, 2001, “Construction delay Computation method Journal of Construction Engineering and Management, 127:60-65.
[3]  Iyer, K.C., and Chaphalkar, N.B., “Understanding HOOH in Construction Project”, Journal of Contracts & Construction Management CE & CR, Sept.2007.
[4]  Mark Sgarlata, A. and Christopher J. Brasco, “Successful claims resolution through an understanding of the law governing allocation of risk for delay & disruption”, Presented at National Conference and Trade show organized by Construction Management Association of America. Sept. 2003.
[5]  James G. Zack, “Calculation and Recovery of Home / Head office overhead”. 3rd World Congress, International Cost Engineering Council, Melbourne, April 2002.
[6]  Karl Silver Berg P.E., 2012, “Construction contract damages: A critical Analysis of ‘Total cost ‘method of valuing damages for extra work”, Journal of Civil rights and Economic development, Vol.17, issue-3, Article-12.
[7]  Hyun- Soo lee, Han-Guk Ryu, Jim Ho Yu and Joe Jumkim “Method for calculating schedule delay considering lost productivity”, Journal of Construction Engineering and Management ASCE, Nov. 2005/1147, 131:1147-1154.
[8]  Stephen Scott, “Delay Claims in UK Contracts”, Journal of Construction Engineering and management ASCE, Sept.1997, 123:238-244.
[9]  Roozbeh Kangari, “Construction Delay documentation in arbitration”. Journal of Construction Engineering and Management ASCE, June 1995/201,121:201-208.
[10]  Michael R. Finke, “Claims for Construction productivity losses”, Journal of Public Contract Law, Vol-26, No.3, Spring 1997 PP 311-318. Published by American Bar association, accessed online www.jstor.org.
[11]  Kululanga G.K., Kuotcha W. and Edumfotwe R., “Construction Contractor’s Claim process Frame work”, Journal of Construction Engineering and Management, July / Aug. 2001/309.
[12]  Gasan G. Kallo, Houston (1996), “Estimating loss of Productivity claims providing proper documentation”, International Journal of Engineering Management. 1996: 12: 13-15.
[13]  Adriana V., Ordonez Olievos and Aminah Rolinson Fayek, “Fuzzy logic approach for activity delay analysis and schedule updating”, Journal of Construction Engineering and Management ASCE, January 2005.131:42.51.
[14]  Ayman H. Al Momani, “Construction Delay: a quantitative analysis”, International Journal of Project Management, 18 (2000) 51-59.
[15]  Codell Parvin, 2016, “Quantification of Damages / Claims”. Publication Blog on Contract administration and claims avoidance.
[16]  David Arditi, Thanat Pattana Kitchmroon, “Selecting a delay analysis method in resolving construction claims”, International Journal of Project management, Sept. 2006, 145-155.
[17]  Srikanth G. and Kumar V.S.S., 2015, “A Parametric study on Construction project delays”, M. Tech. Thesis submitted to, College of Engineering, Osmania University, Hyderabad
[18]  David W. Bardoli and Andrews N. Baldwin, “A methodology for assessing construction project delays”, Journal of Construction Management and Economics (1998), 16, 327-337.
[19]  Derek Nelson, 2014, “Analysis and valuation of disruption”. Online Journal on Project Management, down loaded from website of Hill International Project Construction claims consultants, New Jersey. https://www.hillintl.com.
[20]  Engy Serag, 2006, “Change Orders and Productivity loss quantification using verifiable site data”, Ph.D. Dissertation submitted to Dept. of Civil & Environmental Engineering in College of Engineering and Computer Science, University of Central Florida, Orlando, Florida.
[21]  Issaka N. Kurgi Nuhu Braimah and Rod Gameson, “Delay Analysis within construction contracting organizations”, Journal of Construction Engineering & Management, ASCE Sept. 2008. 134:692-700.
[22]  James G. Zack, and Peter Badala V., 2011, “Pricing contractor- Delay costs”, Construction Forum Navigant Consulting Inc. On line report downloaded.
[23]  Lee Schumancher, P.E., 2014, “Loss of Labour Productivity: Quantification methods and practical considerations”, Construction Claims News letters Published by ARCADIS, Consultancy firm, USA. http://www.arcadisus.com.
[24]  Murat Grundz Yasmin, Neilsen and Mustafa Ozdemir, 2012, “Qualification of Delay factors by Relative Important Index (RII) method for construction projects in Turkey “, Journal of management in Engineering, ASCE. ME 1943 -5479: 0000129, April 2012.
[25]  Nuhu Briamah, “Construction Delay Analysis techniques – A review of application issues and improvement needs”. Journal on Buildings 2013: 3506-53, Open access journal published on 23-7-2013. www.mdpi.com/journal/buildings.