[1] | AACE International, (2012) Recommended Practice No. 18R. 97, Cost Estimate Classification System – As Applied in Engineering, Procurement, and Construction for the Process Industries. AACE International Morgantown, WV, (Latest Version). |
[2] | AACE International, (2009) Recommended Practice No. 42R-08, Risk Analysis and Contingency Determination Using Parametric Estimating, AACE International, Morgantown, WV, 2009. |
[3] | Abdou, A., Lewis, J., and Alzarooni, S. (2007). Modeling Risk for Construction Cost Estimating and Forecasting: A Review. In 28th World Congress on Housing Challenges for 21st Century15 – 19th April, Abu Dhabi UAE. |
[4] | Ahmad, I., (1992). Contingency Allocation: A Computer-aided Approach. AACE Transaction, 28 June – 1 July, Orlando, F. 5. 1-7. |
[5] | Aibinu, A.A., & Jagboro, G.O. (2002). The effects of Construction delays on Project Delivery in Nigerian Construction Industry. International Journal of Project Management. 20, 593-597. |
[6] | Baccarini, D. (2006) The Maturing Concept of Estimating Project Cost Contingency. A Review, 31st Australasian University Building Educators Association Conference (AUBEA 2006). July, 2006) (http://espace.lis.curtin.edu.au/) |
[7] | Baushev, A.N. (2006). Weak Convergence of Probability Measures in Orlicz Spaces. Theory of Probability and Its Application. 40: 3 420-429. |
[8] | Byrne, P. (1996). Risk, Uncertainty and Decision Making in Property Development. 2nd ed. London, UK. E & FN Spon. |
[9] | Chapman, C. and Ward, S. (2000). Estimating and Evaluation of Uncertainty: A Minimalist First Pass Approach. International Journal of Project Management. 18 (6), 369-83. |
[10] | Chen, D. & Hartman, F.T. (2000). A Neural Network Approach to Risk Assessment and Contingency Allocation. AACE Transactions Risk. 07. 01-6. |
[11] | Chentsov, N.N. (2006). Correctness of the Problem of Statistical Point Estimation. Theory of Probability & its Application. 26:1, 13-29. Citation |
[12] | Chuprunov, A.N. (2006). Convergence in Law of Maxima of Independent Identically Distributed Random Variables with Random Coefficients. Theory of Probability and Its Application. 41: 1, 93-97. |
[13] | Clark, D.E. (2001). Monte Carlo Analysis: Ten years of Experience. Cost Engineering, 43 (6), 40-45. |
[14] | Clark, F.D. and Lorenzoni, A.B. (1985). Applied Cost Engineering. New York: M. Dekker. |
[15] | Cooper, D.F. and Chapman, C.B, (1985). Risk Analysis of Construction Cost Estimate. International Journal of Project Management. 3 (3). 141-149. |
[16] | Curran, M.W., (1989). Range Estimating, Cost Engineering 31 (3) 18-26. |
[17] | Dey, P., Tabucanon, M.T. and Ogunlana, S.O. (1994). Planning for Project Control through Risk Analysis; a Petroleum Pipelaying Project. International Journal of Project Management. 12 (1), 23-33. |
[18] | Dickmann, J.E. (1983). Probabilistic Estimating: Mathematics and Applications. Journal of Construction Engineering and Management. 109 (3), 297-308. |
[19] | Dickmann, J.E. and Featherman, W.D. (1998). Assessing Cost Uncertainty: Lessons from Environmental Restoration Projects. Journal of Construction Engineering and Management. 124 (6) 445-451. |
[20] | Flanagan, R.; and Norman, G., (1993). Risk Management and Construction. London, UK: Blackwell Science Ltd. |
[21] | Flyvbjerg, B., From Noble Prize to Project Management: Getting Risks Right, Proe3jct Management Journal, August 2006. |
[22] | Gotze, F. and Zaitsev, A. Yu. (2009). Bounds for the Rate of Strong Approximation in the Multidimensional Invariance Principle. Theory of Probability and Its Application. 53:1, 59-80. |
[23] | Grey, S. (1998). Practical Risk Assessment for Project Management. New York: John Wiley and Sons. |
[24] | Gorodetskii, V. (2006). Convergence Rate in the Invariance Principle for Strongly Mixing Sequences. Theory of Probability and Its Application. 28: 4, 816-821. |
[25] | Hackney, J.W. (1997) Control and Management of Capital Projects, 2nd Edition. AACE International, 1997. |
[26] | Hellerstein, J. and Imbens, G. (1999). Imposing moment restrictions from auxiliary data by weighting. Review of Economics and Statistics. 81, 1-4 |
[27] | Hollmann, J.K., (2007) ‘The Monte-Carlo Challenge: A Better Approach’, AACE International Transactions, AACE International, Morgantown, WV. |
[28] | Imbens, G. (1997). One-Step estimators for over-identified generalized method of moments models. Review of Economics and Statistics. 64, 359-383. |
[29] | Imbens, G., Spady, R., Johnson, R., (1998). Information theoretic approaches to inference in moment condition models. Econometrica. 61, 655-680. |
[30] | Kacinskaite, R., and Laurincikas, A. (2008). A General Discrete Limit Theorem in the Space of Analytic Functions for the Matsumoto Zeta-Function. Theory of Probability and Its Application. 52: 3, 523-531. |
[31] | Leach, L.P. (2003). Schedule and cost buffer sizing how to account for the bias between project performances and your model. Project Management Journal, 34 (2), 34-47. |
[32] | Levine, H. (1995). Risk Management for dummies: Managing Schedule Cost and Technical Risks and Contignency. PM Network, October, 30-32. |
[33] | Lorence, R.B. & Wendling, R.V. (1998). “Basic Techniques for Analyzing and Presenting Cost Risk Analysis”. AACE Transactions, Risk 01. 1-7. |
[34] | Mak, S. & Picken, D. (2000). Using Risk Analysis to Determine Construction Project Contingencies. Journal of Construction Engineering and Management. 126 (2), 130-136. |
[35] | Mak, S., Wong, J., and Picken, D., (1998). The Effect of Contingency Allowances of using Risk Analysis in Capital Cost Estimating: A Hong Kong case study. Construction Management and Economics, 16, 615-519. |
[36] | Merrow, E.W., & Schroeder, M.E., (1990). Assessing Project Cost and Schedule Risk. AACE Transaction. H.6 2-7. |
[37] | Merrow, E.W., Kenneth, E.P., and Christopher W. M., (1981) Understanding Cost Growth and Performance Shortfalls in Pioneer Process Plants, (R - 2569 – DOE), Rand Corporation, 1981. |
[38] | Meschenmoser, D., and Shashkin, A. (2013). Functional Central Limit Theorem for the Measures of Level Surfaces of the Gaussian Random Field. Theory of Probability and Its Application. 57: 1, 162-172. |
[39] | Moselhi, O. (1997). Risk Assessment and Contingency Estimating. AACE Transactions, 13-16th July, Dallas, Dand RM/A 06.1-6. |
[40] | Nevo, A., (2002). Sample Selection and Information – Theoretics Alternatives to GMM. Journal of Econometrics (107). Pp 149-157. Elsevier publishing (available at: http://elsevier.com/locate/econbase |
[41] | Oberlander, G.D. & Trost, S.M. (2001). Predicting Accuracy of Early Cost Estimates based on Estimate Quality. Journal of Construction Engineering and Management. 127(3)173-182. |
[42] | Pack, J.H., Lee, Y.W. and Ock, J.H. (1994). Pricing Construction Risk. Fuzzy Set Appellation. Journal of Construction Engineering and Management. 119 (4), 743-756. |
[43] | Patrascu, A. (1988). Construction Cost Engineering Handbook. New York: M. Dekker. |
[44] | PMI (Project Management Institute) (2000). A Guide to the Project Management body of Knowledge, Upper Darby, P.A: PMI. |
[45] | Qin, J., Lawless, J., (1994). Generalized estimating equations. Annals of Statistics 22, 300-325. |
[46] | Querns, W.R. (1989). What is Contingency Anyway? AACE Transactions. 25 – 28th June. San Diego. B.9. 1-4. |
[47] | Rad, P.F. (2002). Project Estimating and Cost Management. Vienna, VA: Management Concepts. |
[48] | Raftery, J. (1994). Risk Analysis in Project Management. First ed. UK: E & FN Spon. |
[49] | Smith, N.J. (1999). Managing Risk in Construction Projects. Blackwell Science Inc. |
[50] | Thompson, P.A., and Perry, J., (1992). Engineering Construction Risks. London :Thomas Telford. |
[51] | Trost, S.M. and Garold, D.O., (2003) Predicting Accuracy of Early Cost Estimate Using Factor Analysis and Multivariate Regression. Journal of Construction Engineering and Management. Vol.129, (2) pp 198-204 (March/April,). |
[52] | Wideman, R.M. (1992). Project and Program Risk Management: A Guide to Managing Risks and Opportunities. Dexel Hill. Pa: PMI. |
[53] | Williams, T.P. (2003). Predicting Final Cost for competitively bid Construction Projects using Regression Models. International Journal of Project Management. 21. |
[54] | Yeo, K.T. (1990). Risks, Classification of Estimates and Contingency Management. Journal of Management in Engineering 6(4), 4458-470. |