American Journal of Economics
p-ISSN: 2166-4951 e-ISSN: 2166-496X
2012; 2(3): 41-44
doi:10.5923/j.economics.20120203.03
Ulviyya Mammadova
Department of Soils Ecology and Bonitation, Institute of Soilscience and Agrochemistry of ANAS, M.Arif 5, AZ1073, Baki, Azerbaijan
Correspondence to: Ulviyya Mammadova, Department of Soils Ecology and Bonitation, Institute of Soilscience and Agrochemistry of ANAS, M.Arif 5, AZ1073, Baki, Azerbaijan.
| Email: | ![]() |
Copyright © 2012 Scientific & Academic Publishing. All Rights Reserved.
Theprojecting economical advantages of combined solar-wind-biogas energy plant (CSWBEP) was firstly estimated in the paper. For the very plant’s expedient usage instead of fire-wood from forests in mountainous and foothill regions has been taken into consideration. For this purpose the Discount method which is utilized in the currentmarket economy was applied. Discount coefficient is used for economical estimation of investment projects is considered in realization of calculating effectiveness of the plant. By the method economical beneficence of the project was determined in which building and exploitation of CSWBEP during 20 years has been spoken. Taking into account Discount coefficient on the years the project was estimated and economical index of the factors proving project effectiveness was revealed at the result of calculations.
Keywords: Discount coefficient, economical estimation, energy effective
Cite this paper: Ulviyya Mammadova, Economical Estimation of Investment for Combined Solar-Wind-Biogas Energy Plant, American Journal of Economics, Vol. 2 No. 3, 2012, pp. 41-44. doi: 10.5923/j.economics.20120203.03.
);II. Internal profit norm or internal benefit norm (
);III. Profit index or payability index (
);The above mentioned economical rationality rates are defined during calculation of the clean energy project based on CSWBEP.
) is calculated due to the following formula:![]() | (1) |
- discount norm;
- discount periods, year.In investment project realization results can be expressed into money by
indexes. While carrying out the investment project
is determined in the comparison between current incoming money means (
) and investment means cost (
) spent to the very project realization:![]() | (2) |
- discount cost of the current incoming money during the realization of the investment project;
- investment means cost spent fro the realization of the investment projects (money sum). During estimating investment project if
gets negative mark or equals to zero, then the very project realization won’t bring additional income to the investor[10].
internal profit norm or internal benefit norm index characterizes beneficial level of investment project realization. Income index is based on the discount norm. it is expressed by the irrelativeness between future discounted pure coast of the earned money flow from the capital investment and the current cost of the money spent for the project realization [7].![]() | (3) |
- internal profit norm,
– pure discount profit and
- investment capital.Mark of
should be taken in equal to discount norm. In discounting process pure discount profit will be equal to zero.Profit index
is determined by the relation between money means discounted cost gained at the result of project realization and investment cost. ![]() | (4) |
-profit index,
- current discounted cost of the coming money unit while realizing the investment project and
is the investment cost being spent to the project realization. If
gets positive mark, then it will be
>1. whether
gets mark less than unit or equals to unit, then the project isn’t, because this project won’t bring additional profit to investor.
factor is the wide used parameter in economical assessment of the investment projects.
expresses pay-back possibility of expenses spent to investment project realization within minimal duration. In other word
is the factor which reflects time of the additional profit after investment completion to the project.
is calculated by the following:![]() | (5) |
- payback period,
is the investment cost and
is coming money unit depending on the time. How longer
is investment project realization process has greater riskiness rate. In marketing condition this factor is to be taken into considration for implementing investment project.
So, in the presented investment project the obtained pure discounted profit is consists of 847034 AZN. It is that on the mountainous and foothill regions where woodland areas widely extended if this project (in the cost of 1000000 AZN) is realized after 20 years both the spent sum to the project will be paid back and the additional 1558551 AZN profit will be obtained. By using the second method and the indexes at the table on CSWBEP project
- internal profit norm is determined. In this case so discount norm should be revealed that while using it current cost of the money means flow obtained within 20 years can be equalled to the investment coast spent to the project. The searched discounted norm can be found as the follows:
Thus, the project internal profit norm is high. By using the third method and the indexes at the table investment project profit index is calculated as:
Profit index mark is greater than unit, so investment project realization is considered economical beneficent. Thus the spent money to the project can prove itself 2,55 times. By using the fourth method and the indexes at the table spent money for the project implementation pay-back can be calculated:
The pay-back duration of the investment is determined as follows:
So investment resources spent to CSWBEP’s building and exploitation will be paid back during 3,9 years. According to the indexes calculated above, I should notice that the presented investment project actualization is possible. On the mountainous and foothill regions where there are woodlands in order to prevent the forest wood from being hewed for supplying energy demand this project has great importance. Due to the current state and condition the project is advisable from economical and ecological points of view. So, economy of fossil fuels can reduce amount of the hazardous gases to the atmosphere [7].
- 1558551 AZN;● Relation between further discounted pure cost of the money flow gained from the capital investment and current cost of the money spent to the project,
-15,58%;● Relation between the discounted sum of the money means obtained at the result of the CSWBEP project implementation and investment means,
proves itself 2,55 times; ● Depending on the exploitation the total sum of the incoming money means
=255855,1 AZN;● Pay-back duration of the expenses spent to the CSWBEP,
-3,9 years.As the conclusion of the economical estimation, I should notice that the presented investment project on CSWBEP’s application with 1000000 AZN sum is so significant from economical, ecological and energy point of view for protecting the environment. Not only in Pirgulu region but also in any mountainous and foothill regions this project can be realized. For energy demand provision and forest wood economy the project was sufficiently validated. This gives opportunity to decide the investment to the project.| [1] | B.A. Ahmadov. Development Problems of Oil Refining Industry. Baki, «Elm», 2003, 342 p. |
| [2] | B.M. Krivonogov. Improving the Effectiveness of Gas Firing and Environmental Safety. L: Nedra, 1986, 280 p. |
| [3] | F.F. Mammadov., Y.A. Malikov. Economical Aspects of Solar Energy Application in oil Industry. Oil Industry Journal, № 8, 2006, p.p. 47-51. |
| [4] | F.F. Mammadov., Y.A. Malikov. Effectiveness of Solar Energy Application in Crude Oil Dehydration Process. Oil Industry Journal, № 1, 2006, p.p. 54-59. |
| [5] | F.F.Mammadov, U.F.Samadova. Perspectives of Wind Energy Application in . International Scientific Journal «Alternative Energy and Ecology», № 7 (75) 2009, p.p. 52-64. |
| [6] | M.M.Мammadov,Y.А.Мaliкоv, А.М.Ahmadli. Business Plan on Investment Projects. Baki: «Elm», 2000, 165 p. |
| [7] | Malikov Ya.A., Mammadov F.F. Economical aspects of renewable energy application in industry. TPE-2006, . |
| [8] | U.F. Samadova. Solar and Wind Energy Application for the Woods and Forest Soil’s Protection // Renewable Energy Congress X, Glasgow, Scotland, 19-25 July, 2008, p.p 2278-2280. |
| [9] | U.F.Samadova. Effective Protection of Forest Soils in Azerbaijan, International Journal of Academic Research, № 1, vol. 1, 2009, pp. 53-58. |
| [10] | U.F.Samadova. Importance of Solar Energy for the Environment. Municipality and Ecology, existing problems and their possible solution ways, Materials of Scientific Practical Conference. Baki, 2006, pp. 132-135. |
| [11] | U.F.Samadova. Open Evaluation Scale Woodland and Woodless soils (Shamakhi), Ecology and Water Industry (Scientific-Technical and Production) Journal. № 4, 2009, pp. 30-34. |
| [12] | V.V.Shermet, V.M.Pavlyuchenko, V.D.Shapiro and others. Investment Operation. M.: «Vishaya shkola», 1998. 512 с. |